Here are the status updates on the McNeely Lake Park road project:
McNeely Lake Park Mster Plan and Access Road Improvements Updates:
Feb 2, 2012 -The resolution to accept the State funding was introduced at the Metro Council Public Works/Bridges Transportation Committee.
Feb 9, 2012 -The resolution was approved by the Metro Council.
Feb 13, 2012 – The evaluation committee met with the top ranked firm, Gresham, Smith & Partners, to discuss the scope, fee and schedule for the project.
Feb 23, 2012 -The MOA with Ky Transportation Cabinet was signed by the Mayor and delivered to District 5 KYTC.
Feb 24, 2012 -GS&P submitted the scope and fee for the project.
Feb 28, 2012 -The evaluation committee asked for additional information regarding the proposed hours and fees. GS&P provided the additional information the same day. We anticipate having verbal agreement with GS&P by Friday, March 2 and will work with Metro OMB/Purchasing to prepare the purchase order the following week.